This section provides an overview of SECURE-NET project deliverables and their dissemination level. Deliverables classified as Sensitive contain restricted information and are shared only with the European Commission and authorised stakeholders; they are therefore not published on this website. For ease of identification, Sensitive deliverables are displayed in a lighter font and do not include a download link. Deliverables classified as Public can be accessed and downloaded below.
D1
D1.1 – SECURE-NET secondment strategy
Done December 2025
D1.2 – Personal Career Development Plan
Done February 2026
D1.3 – Updated SECURE-NET secondment strategy
Due August 2027
D1.4 – SECURE-NET methodology impact assessment
Due July 2029
D2
D2.1 – Report on the outcomes of secondments I
Due August 2026
D2.2 – Report on the outcomes of secondments II
Due February 2028
D2.3 – Recommendations for strengthening local innovation ecosystems
Due February 2029
D2.4 – Report on the outcomes of secondments III
Due June 2029
D3
D3.1 – Recommendations on implementing cybersecurity measures in times of war
Due August 2027
D3.2 – Report on mutual learning activities I
Due September 2027
D3.3 – Report on mutual learning activities II
Due July 2029
D4
D4.1 – Plan for dissemination, exploitation and communication activities
D4.2 – Interim Report on DEC activities
Due August 2027
D4.3 – Updated plan for dissemination and exploitation including communication activities
Due August 2028
D4.4 – Final report on DEC activities
Due July 2029
D4.5 – SECURE-NET long-term sustainability strategy
Due August 2029
D5
D5.1 – Project Management and Risk Management Plan
Done December 2025
D5.2 – Data Management Plan
D5.3 – Progress report
Due August 2026
D5.4 – Updated Data Management Plan I
Due August 2027
D5.5 – Updated Data Management Plan II
Due July 2029
D6
D6.1 – OEI – Requirement No. 1
Done December 2025